Milestones

Step by step.... the timeline...
  • 14 April 2014 - Paid deposit to McDonald Jones Homes - we are underway!
  • 14 April 2014 - Paid deposit on land - A Binding Contract!
  • 28 May 2014 - Full colour appointment - completed
  • 1 December 2014 - MJH Electrical appointment - completed
  • 16 February 2015 - Super Home appointment - completed
  • 27 April 2015 - Land sent for LPI
  • 9 July 2015 - Land Settlement (October 2015 - Sunset date for registration of land)
  • 2 September 2015 - Build plans submitted to CDC, pending Sydney Water approval stamp
  • 4 September 2015 - Sydney Water approval stamp received and forwarded with to CDC file
  • 25 September 2015 - CDC Approval Recieved, forwarded to ANZ
  • 2 October 2015 - Placed on the Construction List - 20 days to start construction!!!
  • 12 October 2015 - Notified of the Slab Supervisor's name and phone. He will contact us soon.
  • 18 October 2015 - Cut and fill
  • 20 October 2015 - Construction Starts!!!!
  • 22 October 2015 - Meeting with Slab Supervisor Ryan R. - Piers completed
  • 23 October 2015 - drains under slab dug
  • 24 October 2015 - drains completed, covered and capped
  • 14 February 2016 - House is locked up!